Wednesday, March 11, 2009

Nearing Completion of Underground

Doug Electric has almost completed the electrical underground work.












































HVAC branch lines are being installed by Sheldon Mechanical at the new Kitchen/Breakroom.























Con-quest is pouring more curb and gutter at the main entrance.

Posted by Picasa

Thursday, March 5, 2009

Framing and Underground MEP

Framing continues on the mezzanine.






















Many utility trenches have been cut into the slab to accommodate the new plumbing and electrical.






















The slab has been removed at the new Lobby restrooms and electrical systems are being installed underground.





























Underground electrical is being installed in the new training room.






















Curb and gutter work is taking place at the new Entrance.

Posted by Picasa

Tuesday, March 3, 2009

Roofing, Sewer, and more Site Demo

The Roof is being patched and dried in by Stone Roofing






















More Site demo is being completed. Here the old loading dock is being removed.






















Here the off site street work has begun with an excavator removing trees and sidewalk.






















More underground plumbing and electrical work.

Posted by Picasa

Tuesday, February 24, 2009

Underground and Overhead

Framing of the Light Monitor is nearly complete.






















Plumbing rough in work being installed at the new Lobby restrooms.





















New Fire Sprinkler detector check assembly is complete.






















Site Demolition has begun on new planters at Service Entrance.





Posted by Picasa

Tuesday, February 10, 2009

Light Monitor Framing, HVAC, and Metal Studs

Now that the wet weather has passed, work on the roof is progressing. In addition, some of the TI interior work has started including the HVAC and metal stud framing.

Light monitor framing.

































HVAC duct mains and perimeter wall furring at Business Development.



















Closeup view of the cable tensioning system at the glu-lam beams.





















View from the Lobby looking down the spine with new light monitor being framed in.




























Posted by Picasa

Wednesday, January 28, 2009

Brace Frames & Light Monitor

The enormous new structural brace frames have arrived and work has begun to start installing them. In addition, the demolition of the roof to create the new light monitor has also begun.

New brace frame at the Lobby.



























Darren, Greg, Mike, Mark, and Ken supervising.





















The brace frame almost completed.



























Current view from the Lobby looking down the spine.



























The rooftop heat pump HVAC units were set using a helicopter to lift them onto the roof.





















The future 10Kw photovoltaic solar system.


Posted by Picasa

Friday, January 9, 2009

Structural Upgrades Continue

Work is still progressing with the Shell & Core work. Structural work is being put up almost as fast as the concrete panels are being torn down to create the new openings.

Concrete panel is being demolished to create the new main entrance.





















New main entrance from Business Development.



























Steel MC Channels to be installed in the roof structure.



























Some of the roof structure upgrades performed by Archibald Timber Structures.

Posted by Picasa