Tuesday, July 14, 2009

Finishes & Landscaping

We have started to transition into finish work at the new Headquarters as the September move date rapidly approaches. The drywall is 95% complete, the interior glass is 80% complete, and many of the interior lights are up and burning. We will have floor prep starting today and tomorrow in anticipation of the first carpet being laid next Monday. Tile is 95% complete and Fine Line is well on their way getting paint in many of the offices. Here are some of the latest progress photos.

The solar panels have been loaded to the roof and are being readied for installation.





















A current view of the Estimating neighborhood showing drywall nearly taped out, glass installed, and lights on.





















The HVAC ducting, branch electrical, and miles of data cabling are nearly complete.






















Trees have started arriving for the onsite and offsite landscaping.