Ops Meeting 1-Update

Since the Bernards Headquarters Blog is being introduced to half the Company tomorrow, I thought it would be fitting to provide an Ops Meeting Eve update. As Jeff will touch upon tomorrow, we currently are in the weeds of the tenant improvements and site work. Since the last post, decking has continued including the roof of the main conference room. The drywallers and insulators have been right on the heels of the deckers, and the framers are getting close to finishing. Here's the latest construction glossy's for your viewing pleasure!

The 15 foot high metal deck ceiling of the main conference room. The future "cloud" ceiling is framed below it, to be covered with wood paneling soon.






















Drywall being taped at the Operations offices looking North towards Business Development.





















The Accounting Neighborhood is beginning to take shape as the columns that will support the metal brace frames are now in place.

























The recently installed metal deck ceiling at the future I.S. Department bullpen.























Site work has been progressing with the majority of the curb and gutter work complete, as well as the new ramp into the warehouse seen here.