Work continues on the Shell & Core structural work. Archibald Timber Structures has been installing a large amount of framing hardware in the roof to make the building much safer to work in. This has not gone without a hitch though, as we have discovered quite a few discrepancies between the original roof design and what was actually installed by the original builder. This has required quite a bit of modifications to our structural design to make everything fit properly. In addition, much of the footing work has been progressing.
Warehouse brace frame footing excavated.

Accounting brace frame footing excavated.

Steel frames at new Business Development windows.

Lobby brace frame footing excavated and new bathroom slab removed.

Anchor bolts for brace frames.