Another quick update on what's going on at the new Bernards Headquarters. Contracts went out to the Shell and Core Subcontractors which will be KAR Construction for Concrete and two Subs who are new to Bernards. Archibald Timber Structures will handle the panelized roofing and Richwell Steel will have the structural/misc. steel. We continue the demolition removing the upper mezzanine storefront, some site structures and trees and some additional interior elements. The office mock-up is complete and Archibald has begun work on the seismic roof upgrades.
A view from the main gate.
Doug and Greg's offices with new ventilation
The new office mock-up.
Removal of vegetation to increase the views to the park
What people see when they enter San Fernando
Thursday, November 20, 2008